Wow I've been way behind in my updates. Things have been very busy at the Aldea since Sarah and I returned a week ago and a lot has been accomplished in a short amount of time.
A team from CC San Diego arrived two days after us and set to work right away. I am still amazed at the leap forward. It's as if things were lined up just right for them to come in and get a lot done. Here's a quick run down.
- Framed in and screwed plywood siding all around the house.
- Replaced rotten beams in two upstairs rooms and a closet.
Now there is no old wood anywhere in the attic.
- drywalled two bathrooms, a closet, and the two rooms with new beams
- Insulated and drywalled the new porch room.
This is a huge leap forward and kind of a jump start back into things after being away.
We have the added blessing that two members of the team have decided to change their tickets and stay for a second week in order to help out some more. I'm looking forward to having their help and expertise for another week.
Friday, February 1, 2008
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment